Update on 2000, 2003 bonds expenses
I did not receive until after deadline the amounts Guilford County Schools has spent on 2003 bond projects. I intended to include these numbers in the bond update we ran today (not online). Here is the cash flow forecast as of June 15, which includes budget amounts and expenses for the 2000 and 2003 bonds, courtesy of Chief Finance Officer Sharon Ozment.
And, the timeline:
READY FOR START OF SCHOOL
Ready for the start of school
Allen Jay (Southern) Middle, new school
Ferndale Middle, expansion and renovation
Guilford Elementary, new school
Oakview Elementary, expansion and renovation
Pearce Elementary, new school
Reedy Fork Elementary, new school
UNDER CONSTRUCTION
Northern Elementary, new school, target
completion of December 2007
Northern High, new school, January 2008
Parkview Elementary, expansion, December 2007
Pleasant Garden Elementary, expansion, June
2008
UNDER DESIGN
Union Hill Elementary, replacement school, target
completion late 2008
Special Education Center West, new school,
needs additional bond funds to finish
Jamestown Middle, replacement school, needs
additional bond funds to finish
COMPLETE AND OCCUPIED
Florence Elementary, HVAC
Gibsonville Elementary, replacement school
Irving Park Elementary, expansion
Madison Elementary, multipurpose room and
storage
Morehead Elementary, multipurpose room
Peck Elementary, expansion and renovation
Peeler Elementary, multipurpose room
Northern Middle, new school
Northeast High, expansion
Northeast Middle, expansion
Southern High, expansion and renovation
Southwest High, expansion and renovation
Stokesdale Elementary, new classrooms
ON HOLD
Ragsdale High, expansion and renovation, needs
additional bond funds to finish
Guilford Middle, additonal parking